# | Material | Amounts | Rupees (PKR) |
1 | Bricks | 3500 | 12250 |
2 | Bajri | 50 feet | 2150 |
3 | Sand | 100 feet | 1800 |
4 | Cement | 35 bags | 8100 |
5 | Concrete pipe | 4 (12 inches) | 1850 |
6 | Sarya | 8 pieces of 2 sooter(2.5 feet) 2 pieces of 4 sooter(3 feet) | 350 |
7 | Pressure gauge,Handle valve,bush,elbow | 1,1,1,1 | 1000 |
8 | Steel pipe | 1,1 feet length(1 inch) | 200 |
Labour charges:
No | Labor | Days | Cost (PKR) |
1 | Dump digging | 11 days | 10,800 |
2 | Dump construction | 16 days | 19,200 |
Total Expenditure:
Total expenditures for the construction of biogas plant using relatively cheapest materials is 70,000 rupees.
Total expenditures for the construction of biogas plant using relatively cheapest materials is 70,000 rupees.
Time Schedule for the Construction:
# | Schedule | Date |
1 | Class visit (First) for Site Selection | 29-Mar-10 |
2 | Start of dump digging | 1-Apr-10 |
3 | Class visit (Second) | 9-Apr-10 |
4 | Completion of digging dump | 11-Apr-10 |
5 | Class Visit (Third) | 22-Apr-10 |
6 | Start of dump construction | 22-Apr-10 |
7 | 4th class visit | 25-Apr-10 |
8 | Completion of dump construction | 07-May-10 |
9 | Construction of inlet and outlet tanks with lids | 25-May-10 |
10 | 5th Visit | 15-Jub-10 |
Conclusion:
All the material was provided to the place of construction with following characteristics.
- Low cost of material to be purchased.
- Good quality material.
- In time and safely provision.
Thanks to Waseem Ahmad for providing Sats.